The Avenida Azul Trail Fits Inside a County Road Tract, and a Funding Deadline Pushed the Plan Forward

By The Agency Santa Fe

Avenida Azul has no paved shoulder. Its curves and steep road cuts give drivers short sight lines, and the Eldorado Community Improvement Association describes "the large number of pedestrians" who walk on the road to get between two greenbelt trails. Santa Fe County now plans to build a paved hike-bike trail beside it, from Avenida Vista Grande toward Encantado, with completion targeted for the first half of 2027.

Two facts explain this trail. First, the route depends on how Eldorado was laid out: the County owns wide road tracts, so it can fit the trail almost entirely on land it already holds. Second, the push to finish the plan came from money: according to ECIA, the state grant behind the trail has to be spent or encumbered by the end of 2026. The County presents the plan to residents tonight, Thursday, November 19, at 5:30 p.m.

A Road Tract Wider Than the Road

Most subdivisions have a right-of-way, a strip of public land along each road's edge. Eldorado does not. As ECIA's November 2026 Vistas newsletter explains, "there are no road right-of-ways in the Eldorado subdivision." Instead, the County owns large tracts of land that are much wider than the public roads running through them.

That extra width is where the Azul trail goes. The newsletter says the new trail "will lie almost completely within the County's road tract," and it will be paved like the County's other hike-bike trails in Eldorado.

Those other trails make up a large network. ECIA counts about 13 miles of hike-bike paths beside the main roads and calls them multi-use trails. On its Greenbelts and Hike/Bike Map, they are the blue lines. Behind the houses lie 987 acres of greenbelts, which are managed as wild space. They are mainly for walkers, and bicycles and horses are also allowed. Azul is one of the places where the roadside paths and the greenbelt trails fail to connect, and the 1.15-mile project is meant to close that gap.

From a 2020 Request to a 2026 Deadline

The project has been on the books for years. In 2020, ECIA's board asked the County to add the trail to its Infrastructure Capital Improvement Plan list, known as the ICIP, after hearing many requests from homeowners. Later, the County received an initial capital outlay grant from the State Legislature. According to ECIA, a recently passed law requires capital outlay funds to be spent or encumbered by the end of 2026, so County Public Works "has worked hard to finalize this plan so the funding won't be lost."

Milestone Date Source
ECIA board asks County to add trail to ICIP list 2020 ECIA newsletter
Initial state capital outlay grant awarded "Several years ago" ECIA newsletter
Design reported 90% complete August 2026 report Santa Fe County
Design-only completion, as projected in the August report September 30, 2026 Santa Fe County
County informational videoconference November 19, 2026, 5:30 p.m. ECIA newsletter
Deadline to spend or encumber the funds, per ECIA End of 2026 ECIA newsletter
Planned trail completion First half of 2027 ECIA newsletter

The County lists the trail in its August 2026 projects report as the Avenida Azul Eldorado Trail, Project #7720 in District 5. The project manager is Dan Anderson, and the budget is $130,000. The scope reads "design and construct new multi-use trail from Avenida Vista Grande to Encantado Loop covering 1.15 miles." That budget is small next to the other County project at the trail's east end, which is covered further down.

What Changed at the Gallina Park Crossing

At one point the route crosses a large arroyo on the Gallina Park greenbelt. Gallina Park is labeled on ECIA's greenbelt map. An earlier concept called for a bridge there. The current plan uses what the newsletter calls "low water crossings," similar to those on Eldorado's other hike-bike trails where they cross greenbelts.

So this crossing will look like crossings already in use elsewhere in Eldorado, not like a new kind of structure. Anyone who has walked a County hike-bike trail across a greenbelt arroyo has seen the design. The change also keeps Azul in line with the rest of the network the County has built here. Tonight's presentation is the first time the County will walk residents through the revised plan.

Both Ends of the 1.15 Miles

At the west end, the trail starts at Avenida Vista Grande, a main road in the existing path network. At the east end, it reaches the Encantado area, where the County has spent this year on a much larger job.

The Encantado Road Improvements Project began on May 4, 2026. It covers paving the road and updating its drainage infrastructure. When the County announced the project on April 16, it said the work would take about seven months. The contractor is TLC, the engineer is Horrocks, and Tierra Right of Way Services, Ltd. is coordinating temporary work permits with property owners along the corridor. The August projects report lists the Encantado work as a $3.78 million, 1.25-mile project, with substantial completion projected for November 30, 2026.

Here are the two projects side by side, using the County's own figures:

  • Encantado Road: $3.78 million for 1.25 miles of paving and drainage work, with substantial completion scheduled for November 30, 2026
  • Avenida Azul Trail: $130,000 to design and build 1.15 miles of multi-use trail, with completion planned for the first half of 2027

The Encantado project shows how the County runs public meetings on District 5 work. Its April town hall was held in person at the Max Coll Corridor Community Center, 16 Avenida Torreon, with Commissioner Hank Hughes, County staff, the contractor and the engineer on hand. The Azul meeting is a videoconference, so anyone can join from home.

Joining Tonight's Meeting

ECIA's newsletter gives the details.

  1. When: Thursday, November 19, 2026, at 5:30 p.m.
  2. Where: Online by videoconference. ECIA posts the meeting link on eldoradosf.org and sends it by eblast.
  3. Who presents: Representatives from Santa Fe County.
  4. Questions afterward: Dan Anderson with Santa Fe County Public Works, at [email protected].

Questions worth bringing: Where exactly will the low-water crossings sit on the Gallina Park greenbelt? When does construction start within the first half of 2027? How will the new pavement connect to the existing blue-line paths at Avenida Vista Grande and at Encantado Loop?

If you'd like to know how a project like the Avenida Azul trail could change the way a property near it lives day to day, the team at Beth Caldarello is glad to talk it through. Schedule a Private Consultation, and we'll go over the County's plans for your stretch of Eldorado together.

Say Hello!

Giving our clients a curated experience is our number one goal and easing the process of buying and selling homes is our passion.

Follow Us on Instagram